Explanation
Step- 1: Calculating the work they do in 1 day
A does the work in 25 days,
∴ The work A does in 1 day = 125
B does the work in 20 days,
∴ The work B does in 1 day = 120
A's and B's toghether work in 1 day = 125 + 120 = 9100
Step- 2: Solving further
A's and B's work toghether in 5 days = 5 × 9100 = 45100
Work remaining after 5 days = 1 - 45100 = 55100
This work is done by B alone,
∴ Time taken = Work remainingWork B does in 1 day
⇒ Time taken = 55100120 = 11
Hence option B is correct
From Given data, X's 1 day work =18 Y's 1 day work =112 IF X, Y and Z complete the work in 3 days , then Z's 1 day work = One day work of X, Y and Z combined - ( One day work of X + One day work of )
=13−[18+112]
=13−[3+224]
=13−524=8−524=324 Now we have to find Z's share of the salary. X's share: Y's share : Z's share =18:112:324:3:2:3 Z share of wage from the total wage of Rs400=1(3+2+3)×400=Rs150.
Step - 1: Finding number of work units for the first case.
Total 36 men work for a total of 18 days to complete it.
So total work units=36×18=648
Thus, for the first case ,it's a total of 648 work units.
Step - 2: Finding number of days for the second case.
Let it takes x days for the workers to complete the task,so we can write
Number of work units=27×x=27x
Also, the work is same so the work units must be same
So, equating the work units for the two cases, we get
648=27x
x=64827=24
Hence option D is correct
In 21 days 280 m wall build by 72 man
Then in one day 280 m wall build by man =21×72
Or one day one m wall build by man=21×72280
Or one day 100 m wall build by man =21×72×100280
Or 18 days 100 m wall build by man=21×72×100280×18=30 man
Please disable the adBlock and continue. Thank you.