With respect to PERT and​ CPM, slack
  • There is the inherent danger of placing too much emphasis on the critical path.
  • is the amount of time a task may be delayed without changing the overall project completion time.
  • Gantt charts adequately illustrate the interrelationships between the activities and the resources.
  • Min{LS of all immediate following​ activities}.
Which of these time estimates is NOT used in​ PERT?
  • subtasks in major tasks
  • ​Factor-rating method
  • LS and LF
  • standard time
Which of the following sets is determined during a backward​ pass?
  • LS and LF
  • monitoring resources
  • standard time
  • subtasks in major tasks
The latest finish of an activity is
  • Make sure all necessary activities are finished in proper sequence and on time.
  • Min{LS of all immediate following​ activities}.
  • pinpoint activities that need to be closely watched.
  • Managers only need to closely monitor the critical path.