MCQExams
0:0:1
CBSE
JEE
NTSE
NEET
Practice
Homework
×
practice
Pm Chapter 6 Quiz
The main outputs of _____ include work performance measurements, organizational process assets updates, and project document updates.
Report Question
0%
free slack
0%
Defining activities
0%
schedule control
0%
Discretionary
In a network diagram, a(n) _____ is the starting and ending point of an activity.
Report Question
0%
bursts
0%
False
0%
node
0%
True
In project time management, the process of _____ involves deciding how many people, equipment, and materials a project team should use to perform project activities.
Report Question
0%
Estimating activity durations
0%
estimating activity resources
0%
Sequencing activities
0%
Developing the schedule
_____ occurs when a resource works on more than one task at a time.
Report Question
0%
Gantt charts
0%
Multitasking
0%
Project time management
0%
Tracking
A white diamond on a Tracking Gantt chart represents a(n) _____.
Report Question
0%
Lessons-learned reports
0%
slipped milestone
0%
start-to-finish
0%
planning schedule management
The _____ is based on the fact that any complex system at any point in time often has only one aspect or constraint that limits its ability to achieve more of its goal.
Report Question
0%
network diagram
0%
late start date
0%
Theory of Constraints (TOC)
0%
schedule control
_____ involves the processes required to ensure timely completion of a project.
Report Question
0%
determining their dependencies.
0%
Project documents update
0%
Project time management
0%
Multitasking
One of the first reality checks on scheduling that a project manager should make is to review the _____.
Report Question
0%
draft schedule
0%
activity name
0%
longest; shortest
0%
late start date
The _____ is a tabulation of activities to be included on a project schedule.
Report Question
0%
activity list
0%
late start date
0%
Tracking
0%
critical path
_____ states that if something can go wrong, it will.
Report Question
0%
Murphy's Law
0%
project charter
0%
Multitasking
0%
Parkinson's Law
The ultimate goal of developing a realistic project schedule is to provide a basis for monitoring project progress for the _____ dimension of the project.
Report Question
0%
False
0%
templates
0%
time
0%
True
Duration estimates can be provided as a discrete number, a range, or as a(n) _____.
Report Question
0%
Project documents update
0%
determining their dependencies.
0%
three-point estimate
0%
Start-to-start
In the activity defining process, the project team should review the _____ and activity attributes with project stakeholders before moving on to the next step in project time management.
Report Question
0%
activity list
0%
Defining activities
0%
Gantt charts
0%
Developing the schedule
A(n) _____ is a schematic display of the logical relationships among project activities andtheir sequencing.
Report Question
0%
network diagram
0%
activity name
0%
resource breakdown structure
0%
draft schedule
A hierarchical structure that identifies the project's resources by category and type is known as a(n) _____.
Report Question
0%
network diagram
0%
resource breakdown structure
0%
Project documents update
0%
PERT uses different duration estimates whereas CPM uses one specific duration estimate.
A drawback of using _____ or sample files is that managers and their teams might rely heavily on them and ignore unique concerns for their particular projects.
Report Question
0%
templates
0%
False
0%
Dummy activities
0%
activity list
A(n) _____ for a project is the series of activities that determine the earliest time by which the project can be completed.
Report Question
0%
Start-to-start
0%
late start date
0%
Total slack
0%
critical path
In a project schedule, the variable that has the least amount of flexibility is _____.
Report Question
0%
False
0%
node
0%
True
0%
time
The activity list should include the _____, an activity identifier, and a brief description of the activity.
Report Question
0%
schedule control
0%
Start-to-start
0%
activity name
0%
critical path
0:0:1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
0
Answered
0
Not Answered
0
Not Visited
Correct : 0
Incorrect : 0
Report Question
×
What's an issue?
Question is wrong
Answer is wrong
Other Reason
Want to elaborate a bit more? (optional)
Support mcqexams.com by disabling your adblocker.
×
Please disable the adBlock and continue.
Thank you.
Reload page